中船总船舶建造合同格式范本

发布时间 : 星期三 文章中船总船舶建造合同格式范本更新完毕开始阅读

Shipbuilding Contract Hull No._____

3. SUBSTITUTION OF MATERIALS AND/OR EQUIPMENT

In the event that any of the materials and/or equipment required by the Specifications or otherwise under this Contract for the construction of the VESSEL cannot be procured in time to effect delivery of the VESSEL, the SELLER may, provided the SELLER shall provide adequate evidence and the BUYER so agrees in writing, supply other materials and/or equipment of the equivalent quality, capable of meeting the requirements of the Classification Society and of the rules, regulations, requirements and recommendations with which the construction of the VESSEL must comply.

4. BUYER'S SUPPLIED ITEMS

The BUYER shall deliver to the SELLER at its shipyard the items as specified in the Specifications which the BUYER shall supply on Buyer’s account by the time designated by the SELLER.

Should the BUYER fail to deliver to the SELLER such items within the time specified, the delivery of the VESSEL shall automatically be extended for a period of such delay, provided such delay in delivery of the BUYER's supplied items shall affect the delivery of the VESSEL. In such event, the BUYER shall pay to the SELLER all losses and damages sustained by the SELLER due to such delay in the delivery of the BUYER's supplied items and such payment shall be made upon delivery of the VESSEL.

Furthermore, if the delay in delivery of the BUYER's supplied items should exceed fifteen (15) days, the SELLER shall be entitled to proceed with construction of the VESSEL without installation of such items in or onto the VESSEL, without prejudice to the SELLER's right hereinabove provided, and the BUYER shall accept the VESSEL so completed.

The SELLER shall be responsible for storing and handling of the BUYER's supplies as specified in the Specifications after delivery to the SELLER and shall install them on board the VESSEL at the SELLER's expenses.

Upon arrival of such shipment of the Buyer's supplied items, both parties shall undertake an joint unpacking inspection. If any damages are found to be not suitable for installation, the SELLER shall be entitled to refuse to accept the BUYER's supplied items.

21/58

Date: _th ________, 200_

Shipbuilding Contract Hull No._____

ARTICLE VI TRIALS

1. NOTICE

The BUYER and the Supervisor shall receive from the SELLER at least fifteen (15) days notice in advance and seven (7) days definite notice in advance in writing or by telefax or telex confirmed in writing, of the time and place of the VESSEL's sea trial as described in the Specifications (hereinafter referred to as \Trial Run\and the BUYER and the Supervisor shall promptly acknowledge receipt of such notice. The BUYER's representatives and/or the Supervisor shall be on board the VESSEL to witness such Trial Run, and to check upon the performance of the VESSEL during the same. Failure of the BUYER's representatives to be present at the Trial Run of the VESSEL, after due notice to the BUYER and the Supervisor as provided above, shall have the effect to extend the date for delivery of the VESSEL by the period of delay caused by such failure to be present. However, if the Trial Run is delayed more than seven (7) days by reason of the failure of the BUYER's representatives to be present after receipt of due notice as provided above, then in such event, the BUYER shall be deemed to have waived its right to have its representatives on board the VESSEL during the Trial Run, and the SELLER may conduct such Trial Run without the BUYER's representatives being present, and in such case the BUYER shall be obliged to accept the VESSEL on the basis of a certificate jointly signed by the SELLER and the Classification Society certifying that the VESSEL, after Trial Run subject to minor alterations and corrections as provided in this Article, if any, is found to conform to the Contract and Specifications. The SELLER hereby warrants that the necessary visa for the BUYER's representatives to enter China will be issued in order on demand and without delay otherwise the Trial Run shall be postponed until after the BUYER's representatives have arrived at the SELLER's Shipyard and any delays as a result thereof shall not count as a permissible delay under Article VIII thereof. However, should the nationalities and other personal particulars of the BUYER's representatives be not acceptable to the SELLER in accordance with its best understanding of the relevant rules, regulations and/or Laws of the People's Republic of China then prevailing, then the BUYER shall, on the SELLER's telefax or telex demand, effect replacement of all or any of them immediately. Otherwise the Delivery Date as stipulated in Article VII hereof shall be extended by the delays so caused by the BUYER. In the event of unfavorable weather on the date specified for the Trial Run, the same shall take place on the first available day thereafter that the weather conditions permit. The parties hereto recognize that the weather conditions in Chinese waters in which the Trial Run is to take place are such that great changes in weather may arise momentarily and without warning and, therefore, it is agreed that if during the Trial Run of the VESSEL, the weather should suddenly become

22/58

Date: _th ________, 200_

Shipbuilding Contract Hull No._____

unfavorable, as would have precluded the continuance of the Trial Run, the Trial Run of the VESSEL shall be discontinued and postponed until the first favorable day next following, unless the BUYER shall assent by telefax or telex and confirm in writing of its acceptance of the VESSEL on the basis of the Trial Run made prior to such sudden change in weather conditions. In the event that the Trial Run is postponed because of unfavorable weather conditions, such delay shall be regarded as a permissible delay, as specified in Article VIII hereof.

2. HOW CONDUCTED

(a) All expenses in connection with Trial Run of the VESSEL are to be for the

account of the SELLER, who, during the Trial Run and when subjecting the VESSEL to Trial Run, is to provide, at its own expense, the necessary crew to comply with conditions of safe navigation. The Trial Run shall be conducted in the manner prescribed in the Specifications and shall prove fulfillment of the performance required for the Trial Run as set forth in the Specifications.

The course of Trial Run shall be determined by the SELLER and shall be conducted within the trial basin equipped with speed measuring facilities.

(b) The SELLER shall provide the VESSEL with the required quantities of water,

fuel oil and greases with exception of lubrication oil and hydraulic oil which shall be supplied by the BUYER for the conduct of the Trial Run or Trial Runs as prescribed in the Specifications. The fuel oil and greases supplied by the SELLER, and lubricating oil and hydraulic oil supplied by the BUYER shall be in accordance with the applicable engine specifications, and the cost of the quantities of water, fuel oil, lubricating oil, hydraulic oil and greases consumed during the Trial Run or Trial Runs shall be for the account of the SELLER.

3. TRIAL LOAD DRAFT

In addition to the supplies provided by the BUYER in accordance with sub-paragraph (b) of the preceding Paragraph 2 hereof, the SELLER shall provide the VESSEL with the required quantity of fresh water and other stores necessary for the conduct of the Trial Run. The necessary ballast (fresh and sea water and such other ballast as may be required) to bring the VESSEL to the trial load draft as specified in the Specifications, shall be for the SELLER's account.

23/58

Date: _th ________, 200_

Shipbuilding Contract Hull No._____

4. METHOD OF ACCEPTANCE OR REJECTION

(a) Upon notification of the SELLER of the completion of the Trial Run of the

VESSEL, the BUYER or the BUYER's Supervisor shall within six (6) business days thereafter, notify the SELLER by telefax or telex confirmed in writing of its acceptance of the VESSEL or of its rejection of the VESSEL together with the reasons therefor.

(b) However, should the result of the Trial Run indicate that the VESSEL or any

part thereof including its equipment does not conform to the requirements of this Contract and Specifications, then the SELLER shall investigate with the Supervisor the cause of failure and the proper steps shall be taken to remedy the same and shall make whatever corrections and alterations and/or re-Trial Run or Runs as may be necessary without extra cost to the BUYER, and upon notification by the SELLER of completion of such alterations or corrections and/or re-trial or re-trials, the BUYER shall, within six (6) business days thereafter, notify the SELLER by telefax or telex confirmed in writing of its acceptance of its VESSEL or of the rejection of the VESSEL together with the reason therefor on the basis of the alterations and corrections and/or re-trial or re-trials by the SELLER.

(c) In the event that the BUYER fails to notify the SELLER by telefax or telex

confirmed in writing of its acceptance or rejection of the VESSEL together with the reason therefor within six (6) business days period as provided for in the above sub- paragraphs (a) and (b), the BUYER shall be deemed to have accepted the VESSEL.

(d) Any dispute arising among the parties hereto as to the result of any Trial Run

or further tests or trials, as the case may be, of the VESSEL shall be solved by reference to arbitration as provided in Article XIII hereof.

(e) Nothing herein shall preclude the BUYER from accepting the VESSEL with

its qualifications and/or remarks following the Trial Run and/or further tests or trials as aforesaid and the SELLER shall be obliged to comply with and/or remove such qualifications and/or remarks (if such qualifications and/or remarks are acceptable to the SELLER) at the time before effecting delivery of the VESSEL to the BUYER under this Contract.

5. DISPOSITION OF SURPLUS CONSUMABLE STORES

Should any amount of fuel oil, fresh water, or other unbroached consumable

24/58

Date: _th ________, 200_