宁夏进出口岸安全文明施工方案(已审) - 图文

发布时间 : 星期六 文章宁夏进出口岸安全文明施工方案(已审) - 图文更新完毕开始阅读

中能建广电工程局 安全文明施工方案

目 录

一、工程概况 ·················································································································· 2 二、工程安全防护重点 ······································································································ 4 三、管理方针和目标 ········································································································· 4 四、安全保证体系 ············································································································ 5 五、施工部署 ·················································································································· 7 六、项目部各部门安全生产职责 ·························································································· 8 七、各管理人员安全生产责任制 ························································································ 11 八、安全管理措施 ·········································································································· 14 九、安全管理制度 ·········································································································· 15 十、安全技术措施 ·········································································································· 17

1、土方开挖············································································································ 17 2、基坑周边围护 ····································································································· 18 3、脚手架工程安全技术措施 ······················································································ 18 4、起重吊装············································································································ 19 5、焊接工程············································································································ 20 6、高处作业············································································································ 20 7、施工洞口及临边防护和立体交叉作业的隔离 ······························································ 21 8、中小型机具的使用安全 ························································································· 22 9、模板安装安全措施 ······························································································· 25 10、施工临时用电安全技术措施 ·················································································· 26 11、现场防火消防安全 ······························································································ 28 12、雨季施工安全措施 ······························································································ 28 十一、安全事故预控方案 ································································································· 28 十二、文明施工措施┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄29十三、施工现场劳动卫生及职业健康管理措施┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄33 十四、达到“标准化安全文明施工要求”之目的┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄33 附图┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄┄35-42

中能建广电工程局 安全文明施工方案

安全文明施工方案

一、工程概况

1、 本工程位于灵武市河东机场西南侧、银灵高速公路东侧。本项目各子

项工程的慨况见下表:

檐口子项名称 1#、2#监管冷库 植物水果暂扣库 非清真检验冷库 1#监管冷库附属用房 2#监管冷库附属用房 植物水果暂扣库附属用房 非清真检验冷库附属用房 联检大楼 结构体系 楼盖结基础形式 备注 地下设置架 空 层 地下设置架 空 层 地上层数 高度 1 1 1 1 1 1 构 轻型钢屋面 轻型钢屋面 轻型钢屋面 现浇板 现浇板 条形基础 独立基础 条形基础 条形基础 条形基础 12.3 M 轻钢结构 12.3 M 轻钢结构 12.3 M 轻钢结构 7.9 M 7.9M 框架结构 框架架结 7.9M 框架结构 现浇板 独立基础 1 7.9M 框架结构 现浇板 独立基础 地下一层,地上七层30.70M 框剪结构 (局部二层) 地下一层,地上二层 11.6M 框架结构 筏板基础 交易中心 筏板基础 (除联检大楼及交易中心外)所有基础均安照图标要求进行4000KN/米或3000KN/米强夯。

第2页 共45页

中能建广电工程局 安全文明施工方案

2、 各单体建筑面积统计:

A植物水果暂扣库总建筑面积为5813.4M2单层其中:

(1)、轻钢结构为5427.07M2,附属钢筋混凝土用房为386.33M2 (2)、+0.00M以下无架空层。

B、非清真检验冷库总建筑面积为5308.12M2单层其中: (1)、轻钢结构为3333.83M2,附属钢筋混凝土用房为371.57M2. (2)、+0.00M以下架空层按建筑面积计算规则为1602.72M2 C、1#监管冷库总建筑面积为13258.71M2单层其中:

(1)、轻钢结构为7863.297M2附属钢筋混凝土用房1501.623M2, ( 2)、+0.00M以下架空层按建筑面积计算规则为3893.79M2。 D、2#监管冷库总建筑面积为12668.03M2单层其中:

( 1)、轻钢结构为8017.315M2附属钢筋混凝土用房756.925M2, ( 2)、+0.00M以下架空层按建筑面积计算规则为3893.79M2。 E、交易大楼共5508.95M2其中: (1)、地下室:2295.97M2。 (2)、第一层:1666.56M2。 (3)、第二层:1546.42M2。 F、联检大楼共11970.99M2其中: (1)、地下室2449.02M2 (2)、+0.00以上9521.97M2

3、建筑结构安全等级及设计使用年限

2.1建筑结构安全等级:二级

第3页 共45页

中能建广电工程局 安全文明施工方案

2.2结构使用年限:50年 2.3建筑抗震设防类别:丙类 2.4地基基础设计等级:丙级 2.5抗震等级:

钢筋混凝土框架结构抗震等级为二级

二、编制依据

本工程安全生产文明施工方案依据

1、宁夏肉类、水果、种苗指定口岸工程施工图纸及现场实际情况。 2、建筑施工安全检查标准(JGJ59-2011)。 3、建筑施工临时用电安全技术规范

JGJ46-2005)。

4、建筑施工高处作业安全技术规范(JGJ80-91)。

5、建筑施工扣件式钢管脚手架安全技术规范(JGJ130-2011)。 6、建筑机械使用安全技术规程(JGJ33-2001)。 7公司质量、环境、职业健康安全管理手册、文件。

三、本工程安全防护重点

分析本工程实际情况,本工程现场安全防护的重点是;基坑开挖及临边防护安全;机械(塔吊)安全;中小型机具的使用安全;高空作业;脚手架工程;钢筋工程与模板工程的安装与拆卸安全;施工洞口及临边防护和立体交叉作业区的隔离;施工临时用电;消防安全;施工现场和周围人行道的防护隔离措施;冬、雨季施工安全措施。 四、管理方针和目标 1、安全管理目标:

本项目确保市级安全文明标化工程,安全零事故; 杜绝重大伤亡事故,全年负伤率控制在0.25‰以内; 杜绝机械设备事故、火灾事故及重大交通事故;

第4页 共45页