们公司应首先做下列哪项工作?

A. 聘请一名知道该国情况的顾问,向你扼要介绍预计在澳大利亚会出现什么情况 B. 给你一本去澳大利亚的旅游指南,在去澳大利亚的飞机上阅读

C. 在分派前送你去澳大利亚渡过两周,使你了解该地方,会见的新队友

D. 在澳大利亚驻东京大使馆安排一次会见,使你能够见到澳大利亚人,使他们能 够解释日本人在那里生活像什么

148、You have always dreamed of living abroad and now find that you have been selected to manage an international project headquartered overseas. The job sounds exciting, but you must consider certain things. For example, your native language is not spoken there. The weather is terrible: constant rain, high humidity, and occasional earthquakes. The food is completely different, and you will not be able to get those pastries you have loved since you were a child. You will live in an apartment that is half the size of the one you live in currently and that costs twice as much. The cultural differences are many and varied. As you list the pros and cons of accepting the assignment, there is one question, above all others, that you must answer honestly before saying “yes”or “no”. That question is-

A. What common ground exists between the people with whom I will be working and me?

B. How do I translate my cultural awareness and knowledge into functional skills that I can use on the project?

C. How can I continue to refine my skills and to develop my level of cultural competence and adaptability?

D. How adaptable am I?

148、你一直以来梦想在国外生活。现在你被选择到海外的国家项目总部管理项目。这个工作听起来很好,但是你也得考虑一些问题。比如,你说的话当地人不说也不懂。当地气候不好。经常下雨,湿度大,有时地震。饮食习惯完全不同。你将居住的公寓的面积只有现在的一半,租金却贵一倍。文化习惯差异很大。在考虑所有利害关系以后,有一个问题你必须首先做出决定,它是:

A. 我与将要与之一起工作的人的共同点是什么 B. 我如何将自己的文化知识应用到项目上

C. 我如何继续提高自己的能力,发展自己的文化适应能力 D. 我的适应能力如何

149、 A company’s business has been seriously impacted due to cheaper imports. The company creates a project team to explore new product options to increase the revenue from the current value of $100 million. The project team drafts two product options:

Produce A has a 40%chance of increasing revenue to $150 million and a 30% chance of reducing revenue to $60 million due to warranty claims. It also has a 30% chance that there will be no impact on revenue.

Product B has a 50%chance of increasing revenue to $130 million and 20% chance of reducing revenue to $80 million due to warranty claims and litigation. There is a 30% chance that revenue will remain the same.

Which produce provides the best EMV? A. Option A with EMV of $108 million B. Option B with EMV of $111 million

C. Option A with EMV of $111 million D. Option B with EMV of $108 million

149、廉价的进口商品已经严重影响公司的业务。公司组建一支项目团队,开发新产品方案,希望在目前的$1亿营业收入基础上有所提高。项目团队起草了两套产品方案:

产品A有40%的可能性将收入提高到$1.5亿,但有30%可能性因保证索赔使收入会降低至$6000万.还有30%可能性对收入无影响。

产品B有50%的可能性将收入提高到$1.3亿,但有20%可能性因保证索赔和诉讼使收入会降低至$8000万.还有30%的可能性收入将保持不变。 哪项产品能够提供最佳的EMV? A. 方案A,EMV为$1.08亿 B. 方案B,EMV为$1.11亿 C. 方案A,EMV为$1.11亿 D. 方案B,EMV为$1.08亿

150、What is the output of scope planning? A. Work breakdown structure (WBS) B. Scope management plan C. Scope statement D. Project chart

150、收集需求的成果是什么? A. 工作分解结构(WBS) B. 需求管理计划 C. 范围说明书 D. 项目章程

151、A number of tools and techniques are helpful in integrated change control, if you want to assess whether variances form the plan require corrective action, you should use A. Configuration management software

B. A project management information system C. Project status review meetings

D. Performance measurement techniques

151、大量的工具和技术对于整合变更控制的过程是非常有帮助的。如果你想评估偏离了原计划的项目是否需要矫正行为,你应该使用 A. 范围变更管理软件 B. 一个项目管理信息系统 C. 项目状态评估会议 D. 绩效测评技术

152、 An output of close project or phase is the creation of: A. project archives. B. a project charter.

C. a project management plan. D. a risk analysis plan.

152、结束项目或阶段的输出是创建了: