Execution Plan 执行计划

CSA and MEPI Work

土建和机电工程

Construction Execution Plan

土建专项施工方案

2011-06-16

Page 1 of 162 Rev.01

Execution Plan 执行计划 Contents 目录

Chapter 1 Waste Water Sump Construction scheme of deep pit .................................................. 4 第一章 深基坑施工方案 .................................................................................................................. 4 Chapter 2 Measurement Control Scheme for Whole Plant .......................................................... 15 第二章 全厂控制测量方案 ............................................................................................................ 15 Chapter 3 Earth Work ................................................................................................................... 29 第三章 土方工程 ........................................................................................................................... 29 Chapter 4 Formwork Installation Scheme .................................................................................... 33 第四章 模板安装方案 ................................................................................................................... 33 Chapter 5 Rebar Installation Scheme .......................................................................................... 46 第五章 钢筋安装方案 ................................................................................................................... 46 Chapter 6 Concrete Casting Scheme .......................................................................................... 53 第六章 砼浇注方案 ....................................................................................................................... 53 Chapater 7 Scheme for Flatness Controlling of Mass Concrete Slab ......................................... 62 第七章 大面积砼楼面平整度控制方案 .......................................................................................... 62 Chapter 8 Scaffolding ................................................................................................................... 76 第八章 脚手架方案 ....................................................................................................................... 76 Chapter 9 Construction Scheme for Road and Pavement ........................................................... 84 第九章 道路、铺砌施工方案 ........................................................................................................ 84 Chapter 10 Masonry Work ........................................................................................................... 91 第十章 砌体工程 ......................................................................................................................... 91 Chapter 11 Waterproofing ....................................................................................................... 103 第十一章 防水工程 ..................................................................................................................... 103 Chapter 12 Protective Measures in Adverse Seasons .............................................................. 111 第十二章 季节性施工措施 .......................................................................................................... 111 Chapter 13 Decoration Statement .............................................................................................. 116 第十三章 建筑装修方案 .............................................................................................................. 116 1 Plastering 抹灰工程 ............................................................................................................................. 116 2. Dry wall board system 干墙板系统施工方案 ..................................................................................... 120 3. Tiling 瓷砖铺贴施工方案 .................................................................................................................... 124 4. Facing System of Ceiling 吊顶表面系统 .............................................................................................. 140 5 PVC plates of elasticity 弹性PVC地板铺贴 ........................................................................................ 151

Page 2 of 162 Rev.01

Execution Plan 执行计划 6. Application of emulsion 乳胶漆工程施工方案 .................................................................................. 154 7. Construction Scheme of Partition in Bathroom 卫生间隔断施工方案 .............................................. 158

Page 3 of 162 Rev.01

Execution Plan 执行计划

Chapter 1 Waste Water Sump Construction scheme of deep pit

第一章 深基坑施工方案

1 Project in brief

工程概况

(1) General description:RC foundation for FF waste water pond and waste water treatment,

建筑物概况:本工程为消防废水池和污水处理池,钢筋砼基础形式。

(2) Size of the foundation pit: the foundation pit for the waste water pit is sized of 320m2,

braced of 92m by length;

基坑规模:根据本次围护设计方案,消防废水池基坑面积约320m2围护长度约92m.

Excavation depth: the site is to be leveled to 3.36 with the relative elevation of the foundation to the collection pit of ±0.00 (3.35), whose slab is thickening 800mm and bedding course of 100mm; and its relative elevation at the bottom of -5.9M . With given figures, we could work out excavation depths respectively of 5.9m.

基坑开挖深度:本工程取场地平整后标高为3.36,工艺废水池基础底板面相对标高为±0.00 (3.35),底板厚800mm,考虑垫层厚100mm,坑底相对标高为-5.9M,因此基坑开挖深度为5.9m. 2. Ambient and piping

周边环境及管线概况

(1) Ambient

周边环境

The site is quite smooth; thus isolated from the surrounding. 场地较平整,没有建筑物和其它影响

(2) Piping around

周边管线

There is no piping information available yet. Therefore, we will carefully conduct our work and perform necessary protection in case any pipeline found onsite.

暂无基坑周边管线资料,在正式施工、基坑开挖阶段如发现管线,应加强管线监测,确实做好管线保护工作。

3.Construction plan compiling basis

施工方案的编制依据

3.1.Existing construction & installation policies, rules, regulation and standards in Taicang city

and in China;

Page 4 of 162 Rev.01