上建机电 TITLE:直流系统及不间断电源(UPS)安装检验测试计划 Inspection & Test Plan of Installation of DC System and UPS ITP itp PROJECT PROJECT NO. UNIT Celanese VAE Expansion Project CC0911E1328 VAE SHEET: 1 of 2 REV 1 DOCUMENT NO :VAE-ITP-SMEICCriticality Class: III Inspection level: LPI No. Inspection/Test Item UPS Installation 不间断电源(UPS)安装 Standard Designing Documents 设计文件 SMEIC NHSC MWP QISS MASTER PIECE REFERENCE SH/T3903-2004-A.4 SH/T3503-2007-J506 15.0 I/R W/R GB50172-92 Technical Orientation Drawing & Documents 技术交底 15.1 图纸文件 Material Approval 15.2 材料报审 Material Review 15.3 材料报验 GB50172-92 Designing Documents 设计文件 Drawing & Documents 图纸文件 Foundation Resurveying 基础复测 GB50172-92 Drawing 图纸 R A.4 G111 R R R A.4 I/R H/R H/R A.9 15.4 I/R W/R A.4 J204 15.5 15.6 15.7 15.8 GB50172-92 Acceptance of Drawing Foundation Transfer 图纸基础交接验收 GB50172-92 Installation of Base Drawing Shape Steel Rack 图纸底座型钢架安装 GB50172-92 Installation of Panel Drawing and Cabinet 图纸盘柜安装 GB50172-92 Installation of Drawing Earthing Routine 图纸接地线路安装 GB50172-92 R H/R H/R A.4 I/R W/R A.4 J506 I/R W/R A.4 J506 I/R W/R A.4 J118 Note:

1.Abbreviations: R-Review W-Witness H-Hold I/R-Inspect/Report (Record) W/R-Witness/Report (Record) Review ()-Spot or Random /-And

上建机电 TITLE:直流系统及不间断电源(UPS)安装检验测试计划 Inspection & Test Plan of Installation of DC System and UPS ITP PROJECT PROJECT NO. UNIT Celanese VAE Expansion Project CC0911E1328 VAE SHEET: 2of 2 REV 1 DOCUMENT NO.: VAE-ITP-SMEICCriticality Class: III Inspection level: LPI Wire Check & Wire Connection 15.9 校线接线 Drawing 图纸GB50172-92 I/R W/R A.4 J506 15.10 Insulation Resistance Test 绝缘电阻测试 Drawing 图纸GB50172-92 Standard Drawing 图纸GB50172-92 Drawing 图纸GB50172-92 Technical Documents 技术文件 I/R W/R I/R W/R A.4 J506 I/R W/R A.4 J506 SMEIC NHSC MWP QISS MASTER PIECE REFERENCE I/R W/R A.4 J507 No. Inspection/Test Item Electrical Regulation15.11 电气调试 Battery Assembly 15.12 蓄电池组装 Charge/Discharge Test 15.13 充放电试验 Inspection Run-in Test 15.14 试运行前检查 A.4 J506 G523/1-2 GB50172-92 Prior Drawing & Documents 图纸文件 R H/R H/R A.4 J506 GB50172-92 Run-in Test of the Technical Whole Machine Documents 15.15 整机试运行 of 技术文件 GB50172-92 Acceptance Intermediate 15.16 Transfer 中间交接验收 Drawing & Documents 图纸文件 I/R H/R H/R A.4 J506 SH/T3903-2004-A10 SH/T3904-2005 SH/T3503-2007-J106A/B R H/R H/R H/R Note:

1.Abbreviations: R-Review W-Witness H-Hold I/R-Inspect/Report (Record) W/R-Witness/Report (Record) Review ()-Spot or Random /-And

联系合同范文客服:xxxxx#qq.com(#替换为@)